Project Overview
Neath Port Talbot Council is currently undertaking works to reroute the east outfall into the west outfall at Bay Campus.
Excavation works will begin behind the Great Hall and extend approximately 300 metres through the sand dunes to the SSSI. The works will involve the installation of a new drainage route connecting the two outfalls.
Project Impacts
The works will affect areas surrounding the Great Hall, the sand dunes, and sections of the beach.
Excavation activities may generate noise, particularly during the initial stages of the project near the Great Hall. Noise levels are expected to reduce as work progresses towards the SSSI.
Heavy plant and machinery, including JCBs, dumper trucks, and other construction vehicles, will primarily access the site via the east side of the campus using Engineering East Road. Some vehicles may also be diverted around the School of Management and Great Hall buildings.
Traffic management measures will be in place throughout the duration of the project. No parking will be permitted on both sides of designated roads to allow large vehicles sufficient space to manoeuvre. Disabled parking bays will remain accessible.
Staff, students, and visitors should be aware of the main plant entrance located on the east side of the campus near the SSSI. Access routes to the beach will remain available and will be clearly signposted.

No parking will be permitted on the yellow line due to space required to manoeuvre heavy machinery. Disabled bays will still be accessible.
Project Timeline
Works are expected to continue for approximately 12 weeks. Traffic management measures and access restrictions will remain in place for the duration of the project.